A new system development project is running late against a critical implementation deadline. Which of the following is the MOST important activity?

  • A. Ensure that code has been reviewed.
  • B. Perform user acceptance testing (UAT).
  • C. Document last-minute enhancements.
  • D. Perform a pre-implementation audit.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
FAGFUR
4 months ago
Selected Answer: B
In the context of a new system development project running late against a critical implementation deadline, the most important activity is to perform user acceptance testing (UAT). User acceptance testing is a critical phase in the development process where end-users validate whether the system meets their requirements and expectations. Identifying and addressing any issues during UAT is crucial before the system is implemented, as it helps ensure that the system functions as intended and meets the needs of the users.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago