Question #: 1
Topic #: 1
[All CCAK Questions]

Changes to which of the following will MOST likely influence the expansion or reduction of controls required to remediate the risk arising from changes to an organization’s SaaS vendor?

  • A. Risk exceptions policy
  • B. Contractual requirements
  • C. Risk appetite
  • D. Board oversight
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Muchanetsa
3 days, 8 hours ago
C is the correct answer. If the change/s introduces additional risk, - the risk appetite and tolerance can determine if the organization is willing to take or tolerate the introduced risk.
upvoted 1 times
...
nksil
1 month, 2 weeks ago
Correct answer is C
upvoted 1 times
...
[Removed]
2 months, 1 week ago
Selected Answer: B
B. Contractual requirements
upvoted 1 times
...
SumiRay
4 months, 3 weeks ago
Risk Appetite, risk exception policy and board oversight of an organization does not change due to a change in a service provider and the question does not refer to changes in risk methodology of the organization. Hence, considering same, the changes will only be in the contractual agreements of the new service provider. Thereby referring to ats20 response below, the number of controls will either increase or decrease due to changes in contractual requirements with the new SaaS provider.
upvoted 2 times
...
ats20
10 months, 4 weeks ago
Selected Answer: B
The contractual requirements are the MOST likely to influence the expansion or reduction of controls required to remediate the risk arising from changes to an organization’s SaaS vendor. Contractual requirements define the terms and conditions of the agreement between the organization and the SaaS vendor, including the security and compliance requirements. Therefore, any changes to the contractual requirements can impact the controls required to remediate the risk arising from changes to an organization’s SaaS vendor.
upvoted 2 times
...
AlfredP
1 year, 3 months ago
C, the reason being Risk Appetite can influence either expansion/ reduction.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...