Question #: 409
Topic #: 1
[All CISA Questions]

Which of the following is MOST important for an IS auditor to assess during a post-implementation review of a newly modified IT application developed in-house?

  • A. Rollback plans for changes
  • B. Sufficiency of implemented controls
  • C. Updates required for end user manuals
  • D. Resource management plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Swallows
1 month ago
Selected Answer: B
While rollback plans for changes (Option A) are important for mitigating risks associated with implementation issues or unforeseen consequences of modifications, the sufficiency of implemented controls is of greater importance during a post-implementation review. Assessing the sufficiency of controls ensures that appropriate measures are in place to manage risks, protect data, maintain system integrity, and ensure compliance with relevant policies, standards, and regulations.
upvoted 2 times
...
Changwha
11 months, 4 weeks ago
B. Sufficiency of implemented controls
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel