Question #: 358
Topic #: 1
[All CISA Questions]

Which of the following would BEST manage the risk of changes in requirements after the analysis phase of a business application development project?

  • A. Sign-off from the IT team
  • B. Quality assurance (QA) review
  • C. Ongoing participation by relevant stakeholders
  • D. Expected deliverables meeting project deadlines
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Swallows
1 month ago
Selected Answer: C
While a Quality Assurance (QA) review (Option B) is important for ensuring that the developed application meets quality standards and requirements, it typically occurs after the development phase. Ongoing participation by relevant stakeholders, on the other hand, helps proactively manage changes in requirements before they impact the project timeline, budget, and scope. Therefore, it is the best approach for managing the risk of changes in requirements during business application development projects.
upvoted 2 times
...
Changwha
12 months ago
C. Ongoing participation by relevant stakeholders
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.