Question #: 261
Topic #: 1
[All CISA Questions]

An organization has replaced all of the storage devices at its primary data center with new, higher capacity units. The replaced devices have been installed at the disaster recovery site to replace older units. An IS auditor's PRIMARY concern would be whether:

  • A. the recovery site devices can handle the storage requirements.
  • B. the procurement was in accordance with corporate policies and procedures.
  • C. the relocation plan has been communicated to all concerned parties.
  • D. a hardware maintenance contract is in place for both old and new storage devices.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Sibsankar
3 months, 3 weeks ago
D should be right answer
upvoted 1 times
...
Swallows
7 months, 1 week ago
Selected Answer: A
The audit point is to verify that the replaced device meets the requirements and is operational at the recovery site.
upvoted 2 times
...
BA27
1 year ago
B. the procurement was in accordance with corporate policies and procedures.
upvoted 1 times
...
hoho
1 year, 4 months ago
A, not really, requirement seem little important
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...