Which of the following methods enables the MOST rigorous testing while avoiding the disruption of normal business operations?

  • A. Walk-through test
  • B. Full interruption test
  • C. Parallel test
  • D. Checklist review test
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Jess20
1 month, 1 week ago
Selected Answer: C
C AIO Peter H. Gregory 2nd edition Page 482 A parallel test is so named because, as live production systems continue to operate, the backup IT systems are processing business transactions in parallel, to test whether both systems process transactions equally well.
upvoted 1 times
...
Nillanash
6 months, 2 weeks ago
C-Parallel test. It is the best answer because it is done concurrently at the test site and the organization site there by allowing businesses operations to continue uninterrupted.
upvoted 1 times
...
richck102
6 months, 2 weeks ago
Selected Answer: C
C. Parallel test
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.