Question #: 381
Topic #: 1
[All CISM Questions]

Which of the following is the FIRST step in developing a business continuity plan (BCP)?

  • A. Identify critical business processes.
  • B. Determine the business recovery strategy
  • C. Determine available resources
  • D. Identify the applications with the shortest recovery time objectives (RTOs)
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
oluchecpoint
7 months, 2 weeks ago
A. Identify critical business processes. The first step in developing a business continuity plan (BCP) is to identify critical business processes. This step involves conducting a thorough assessment of your organization's operations to determine which processes are essential for its continued functioning. Once you have identified these critical processes, you can then proceed to determine the business recovery strategy, available resources, and other elements of the BCP.
upvoted 2 times
...
AaronS1990
7 months, 4 weeks ago
Selected Answer: A
From CISM Certified Information Security Manager Study Guide by Mike Chappell 1. Project Scope and Planning As with any formalized business process, the development of a resilient business continuity plan requires the use of a proven methodology. Organizations should approach the planning process with several goals in mind: Perform a structured review of the business’s organization from a crisis planning point of view. (A) Create a BCP team with the approval of senior management. Assess the resources available to participate in business continuity activities. (C) Analyse the legal and regulatory landscape that governs an organization’s response to a catastrophic event. (B)
upvoted 3 times
...
Agamennore
7 months, 4 weeks ago
Selected Answer: A
You need FIRST to identify critical business process… so the answer is A. You will find people and team AFTER to know WHAT to do… not before
upvoted 1 times
...
Goseu
9 months ago
Selected Answer: C
C is the correct answer . Finding people and Team assembly . Identifying critical business processes/priorities is the second step which is BIA. 1. Project scope and planning 2. Business impact assessment 3. Continuity planning 4. Approval and implementation. 5. Maintenance 6. Testing and exercise
upvoted 1 times
AaronS1990
7 months, 4 weeks ago
What about Project scope though? you haven't broken it down at all. It's A, I'll explain why
upvoted 2 times
...
...
richck102
10 months, 1 week ago
Selected Answer: A
A. Identify critical business processes.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago