Question #: 60
Topic #: 1
[All CGEIT Questions]

An enterprise has a large backlog of IT projects. The current strategy is to execute projects as they are submitted, but executive management does not believe this method is optimal. Which of the following is the MOST important action to address this concern?

  • A. Establish a performance dashboard that determines business value.
  • B. Create a combined business/IT committee to determine project prioritization.
  • C. Implement a methodology to prioritize projects based on resource availability.
  • D. Implement stage-gating to determine the value of each project.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MDMA786
3 months, 3 weeks ago
Selected Answer: B
The answer is B, the combined team will prioritise projects for delivery while d: Stage Gating occurs after project kickoff.
upvoted 1 times
...
Zumbaman
6 months, 3 weeks ago
B.Creating a combined business/IT committee can help ensure that IT projects are prioritized based on their alignment with business objectives and their potential to deliver value to the business. This approach can help to ensure that the most important projects are executed first, which can lead to more effective use of IT resources and better outcomes for the business.
upvoted 1 times
...
shiowbah
7 months, 3 weeks ago
B. Create a combined business/IT committee to determine project prioritization.
upvoted 1 times
...
Sathish5
10 months, 3 weeks ago
Selected Answer: D
Taken from ISACA CGEIT Review Manual 8th Edition - Stage-gate—A point in time when a program is reviewed and a decision is made to commit expenditures to the next set of activities on a program or project, to stop the work altogether, or to put a hold on execution of further work. Answer D is correct. Please observe the question correctly and not blindly follow the answer from Chat GPT.
upvoted 3 times
...
Frank1480
1 year, 5 months ago
The most important action to address the concern of a large backlog of IT projects and the suboptimal execution strategy would be: B. Create a combined business/IT committee to determine project prioritization. By establishing a combined business/IT committee, the organization can bring together key stakeholders from both the business and IT departments. This committee can assess and prioritize projects based on various factors such as strategic alignment, business value, resource availability, and project feasibility. This collaborative approach ensures that project prioritization decisions are made with a holistic understanding of both business objectives and IT capabilities. It also helps in fostering communication, coordination, and consensus among different stakeholders, leading to better decision-making and more efficient allocation of resources.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...