Which of the following is the PRIMARY benefit of implementing a maturity model for information security management?

  • A. Gaps between current and desirable levels will be addressed.
  • B. Information security management costs will be optimized.
  • C. Information security strategy will be in line with industry best practice.
  • D. Staff awareness of information security compliance will be promoted.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Odisman1
3 months, 2 weeks ago
C maturity model is used to assess the security state of an organisation against industry benchmarks
upvoted 1 times
...
Jess20
1 year ago
Selected Answer: A
A- Maturity models identify the gaps between the current state of the governance process and the desired state. This helps the organization to determine the remediation steps required for improvement
upvoted 1 times
...
sphenixfire
1 year, 2 months ago
Selected Answer: D
How mature are you in contrast to...
upvoted 1 times
...
richck102
1 year, 5 months ago
Selected Answer: A
A. Gaps between current and desirable levels will be addressed.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...