Exam CISA topic 1 question 1095 discussion

Actual exam question from Isaca's CISA
Question #: 1095
Topic #: 1
[All CISA Questions]

Which of the following is the BEST evidence that a project is ready for production?

  • A. A parallel test over a full processing cycle has been successful.
  • B. A pilot implementation with reduced scope has been tested and approved.
  • C. A detailed conversion plan has been rehearsed in two desktop exercises.
  • D. Rollback procedures have been successfully tested.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
3008
Highly Voted 10 months, 1 week ago
Selected Answer: A
a is answer
upvoted 5 times
...
FAGFUR
Most Recent 4 months ago
Selected Answer: A
The best evidence that a project is ready for production is that a parallel test over a full processing cycle has been successful. A parallel test involves running the new system concurrently with the existing system to ensure that they produce consistent and accurate results. Success in a full processing cycle indicates that the new system can handle the workload and perform as expected in a real-world scenario.
upvoted 4 times
...
BabaP
10 months, 1 week ago
Selected Answer: A
Why not A?
upvoted 3 times
...
saado9
10 months, 2 weeks ago
A. A parallel test over a full processing cycle has been successful.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.