A system development project is experiencing delays due to ongoing staff shortages. Which of the following strategies would provide the GREATEST assurance of system quality at implementation?

  • A. Utilize new system development tools to improve productivity.
  • B. Deliver only the core functionality on the initial target date.
  • C. Implement overtime pay and bonuses for all development staff.
  • D. Recruit IS staff to expedite system development.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Precept
Highly Voted 1 year, 6 months ago
Selected Answer: D
None of the other options addresses the underlying issue of staff shortage
upvoted 6 times
...
PurpleParrot
Most Recent 3 months ago
Selected Answer: B
the quality concern is only addressed by B. option D would also take time, training!
upvoted 1 times
...
analuisamoreira
4 months, 3 weeks ago
Selected Answer: B
Terrible question. It depends much on the company's contex, and there is much missing information on that. How am I supposed to know that hiring staff will be approved? I real life that process usually takes several months and probably an ongoing project would delay anyway.
upvoted 1 times
...
Swallows
7 months, 1 week ago
Selected Answer: B
Since the question is about the development of a Minimum Viable Product, B is the correct answer.
upvoted 1 times
...
akosigengen
8 months, 3 weeks ago
Selected Answer: B
B is the answer
upvoted 1 times
...
Rachy
10 months, 1 week ago
Selected Answer: B
Answer is B oh
upvoted 1 times
...
JustCisa
1 year ago
Selected Answer: B
no way IS staff can do development, makes no sense Answer is B
upvoted 2 times
...
BA27
1 year, 2 months ago
B. Deliver only the core functionality on the initial target date. Can't be D since IS staff cannot develop
upvoted 2 times
...
007Georgeo
1 year, 6 months ago
Selected Answer: B
Should be B
upvoted 2 times
...
oorami
1 year, 8 months ago
Selected Answer: B
I think the answer is B
upvoted 2 times
...
saado9
1 year, 8 months ago
B. Deliver only the core functionality on the initial target date.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...