You are the risk official in Bluewell Inc. You are supposed to prioritize several risks. A risk has a rating for occurrence, severity, and detection as 4, 5, and 6, respectively. What Risk Priority Number (RPN) you would give to it?
Suggested Answer:A🗳️
Steps involving in calculating risk priority number are as follows: ✑ Identify potential failure effects ✑ Identify potential causes ✑ Establish links between each identified potential cause ✑ Identify potential failure modes ✑ Assess severity, occurrence and detection ✑ Perform score assessments by using a scale of 1 -10 (low to high rating) to score these assessments. ✑ Compute the RPN for a particular failure mode as Severity multiplied by occurrence and detection. RPN = Severity * Occurrence * Detection Hence,
RPN = 4 * 5 * 6 - = 120 Incorrect Answers: B, C, D: These are not RPN for given values of severity, occurrence, and detection.
To calculate the Risk Priority Number (RPN), you can use the formula:
RPN = Occurrence x Severity x Detection
In this case, the values are:
Occurrence = 4
Severity = 5
Detection = 6
So, RPN = 4 x 5 x 6 = 120
Therefore, the correct RPN for this risk is A. 120.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
SuperMax
1 month, 3 weeks agoGhostclown
9 months, 1 week agoChemngoremmercy
1 year, 1 month agoldl
1 year, 8 months ago