You are the project manager of GHT project. You have identified a risk event on your project that could save $100,000 in project costs if it occurs. Which of the following statements BEST describes this risk event?
A.
This risk event should be mitigated to take advantage of the savings.
B.
This is a risk event that should be accepted because the rewards outweigh the threat to the project.
C.
This risk event should be avoided to take full advantage of the potential savings.
D.
This risk event is an opportunity to the project and should be exploited.
Suggested Answer:D🗳️
This risk event has the potential to save money on project costs, so it is an opportunity, and the appropriate strategy to use in this case is the exploit strategy. The exploit response is one of the strategies to negate risks or threats appear in a project. This strategy may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized. Exploiting a risk event provides opportunities for positive impact on a project. Assigning more talented resources to the project to reduce the time to completion is an example of exploit response. Incorrect Answers: A, C: Mitigation and avoidance risk response is used in case of negative risk events, and not in positive risk events. Here in this scenario, as it is stated that the event could save $100,000, hence it is a positive risk event. Therefore should not be mitigated or avoided. B: To accept risk means that no action is taken relative to a particular risk; loss is accepted if it occurs. But as this risk event bring an opportunity, it should me exploited and not accepted.
D. This risk event is an opportunity to the project and should be exploited.
Explanation:
Option A suggests mitigation, but in this context, the risk is seen as an opportunity rather than a threat that needs mitigation.
Option B mentions accepting the risk, but it doesn't capture the proactive stance of exploiting the opportunity.
Option C suggests avoidance, which may not be the best approach when the risk presents a potential benefit.
Therefore, option D is more aligned with the idea of treating the risk as an opportunity and actively seeking to exploit it for the project's benefit.
Because = pro and cons (expressing an explanation or reason)
Exploit= take advantage without looking at negative effects
(make full use of and derive benefit from (a resource)
I contest the answer (D): I believe B is more accurate.
"accepted" shouldn't be the defining factor as the key word.
The statement: "because the rewards outweigh the threat" indicates to me that it was reviewed in some way and a conclusion was made y vs D. that says lets just take advantage.
D. This risk event is an opportunity to the project and should be exploited.
In risk management, a risk event that could have a positive impact on the project is considered an opportunity. In this case, the risk event could save $100,000 in project costs, which is a favorable outcome for the project. To take advantage of this opportunity, it should be exploited or managed in a way that maximizes the potential savings. Therefore, option D is the most appropriate response.
D. This risk event is an opportunity to the project and should be exploited.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
SuperMax
1 month, 3 weeks agostayshock
9 months agostayshock
9 months agoChemngoremmercy
1 year, 1 month agoldl
1 year, 8 months ago