exam questions

Exam M3-123 All Questions

View all questions & answers for the M3-123 exam

Exam M3-123 topic 1 question 43 discussion

Actual exam question from Infor's M3-123
Question #: 43
Topic #: 1
[All M3-123 Questions]

Which one of the following activities involves manual updating for an invoiced customer order?

  • A. Invoice post-processing
  • B. Closing the order line
  • C. Automatic allocation
  • D. Bank statement processing
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
pip1234
2 months, 1 week ago
Selected Answer: A
'CO Invoice. Post-Process' (OIS196) allows users to manually update various aspects of an invoiced customer order after the invoice has been generated.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...