Actual exam question from IIBA's CBAP
Question #: 257
Topic #: 1
[All CBAP Questions]

Which of the following processes is must at the end of each project phase to determine the completeness of the project work and to gain the customer's acceptance to move the project forward?

  • A. Scope verification
  • B. Inspection of key results
  • C. Quality control
  • D. Phase gate review
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Farooq_95
2 months, 2 weeks ago
Selected Answer: D
A question from PMBOK. PMBOK defines "Phase Gate Review" as A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or program. Other options are incorrect: Scope verification (option A) involves formal acceptance of completed project deliverables by stakeholders to ensure that they meet the agreed-upon requirements and specifications. Inspection of key results (option B) may involve reviewing specific project outcomes or milestones but may not necessarily occur at the end of each project phase. Quality control (option C) focuses on monitoring and verifying that project deliverables meet quality standards but may not specifically address the completeness of project work at the end of each phase.
upvoted 2 times
...
teehmama
8 months ago
Phase gate reviews are more about overall project progress and decision-making, while scope verification is focused on validating individual deliverables against requirements.. SCOPE VERIFICATION seems more like it
upvoted 1 times
...
raf79
1 year ago
The phase gate process is a technique that is used to guide a project from conception to launch. It requires a review of each project stage before moving on to the next. In the phase gate review process, specific criteria must be met to determine the success of a phase and the ongoing viability of a project.
upvoted 1 times
...
Dillon91
1 year, 5 months ago
D I believe
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago