Question #: 52
Topic #: 1
[All ECBA Questions]

Which cost is estimated based on the alternative results that might have been achieved if the resources devoted to one design option had been allocated to another design option?

  • A. Implementation
  • B. Maintenance
  • C. Opportunity
  • D. Purchase
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Adnan8t2
5 months, 2 weeks ago
Selected Answer: C
Page 159 Opportunity costs are alternative results that might have been achieved if the resources, time, and funds devoted to one design option had been allocated to another design option.
upvoted 1 times
...
Hazemnz
1 year ago
Selected Answer: C
BABOK page 159
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.