C
Approval of requirements and designs may be formal or informal. Predictive
approaches typically perform approvals at the end of the phase or during planned
change control meetings. Adaptive approaches typically approve requirements
only when construction and implementation of a solution meeting the
requirement can begin.
ANSWER: C
Page 95 – BABOK V3
Approval of requirements and designs may be formal or informal. Predictive approaches typically perform approvals at the end of the phase or during planned change control meetings.