Actual exam question from IIBA's ECBA
Question #: 14
Topic #: 1
[All ECBA Questions]

Which activity is a business analyst (BA) performing when ensuring that a set of requirements is developed with enough detail to be usable by a particular stakeholder?

  • A. Validating requirements
  • B. Verifying requirements
  • C. Eliciting requirements
  • D. Specifying requirements
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
alir20
3 months, 3 weeks ago
Answer B 7.2 Verify Requirements 7.2.1 Purpose The purpose of Verify Requirements is to ensure that requirements and designs specifications and models meet quality standards and are usable for the purpose they serve
upvoted 1 times
...
Adnan8t2
1 year, 8 months ago
ANSWER: B Page 134 – BABOK V3 Verify Requirements: ensures that a set of requirements or designs has been developed in enough detail to be usable by a particular stakeholder,
upvoted 2 times
...
Hazemnz
2 years ago
Selected Answer: B
BABOK page 141
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago