Question #: 147
Topic #: 1
[All CBAP Questions]

You are the business analyst for the NHQ Project. You have identified several stakeholders that need different types of information related to the requirements.
Which stakeholder would need detailed technical interface requirements?

  • A. Project manager
  • B. Regulators
  • C. Testers
  • D. Implementation subject matter experts
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
bim_269
6 months, 3 weeks ago
BABOK V3 Pg 17 - 19: The Implementation SME is anyone with knowledge as regards the implementation of one or more solution while testers only ensure that the solution meets the requirement as defined. so the implementation SME is the one that needs the detailed technical interface requirements as he implements solution which may also interface with other solution
upvoted 3 times
...
Wlkkkk
8 months ago
why not c
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago