C. More effort is needed to trace requirements.
Explanation:
As the number of requirements or the level of formality increases, the complexity and the need for detailed management also increase. Specifically, the effort required to trace requirements grows significantly. This is because:
C is correct. More effort is required to trace requirements when the level of formality or number of requirements increases.
upvoted 8 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
SajaAlznaidi
Highly Voted 1 year, 7 months agoSimoneV28
Highly Voted 1 year, 7 months agoherodes
Most Recent 1 month agoamd112b
3 months, 2 weeks agoLindie_Botha
6 months, 3 weeks agoAdnan8t2
1 year, 1 month agoamrita0204
1 year, 3 months agoBMM_76
1 year, 3 months agom4tim4ti
1 year, 4 months agoA_pe
1 year, 4 months agoHazemnz
1 year, 5 months agoHazemnz
1 year, 5 months agoThroneroom
1 year, 7 months ago