You are the business analyst for your organization. Your stakeholders have recently reviewed and approved the set of requirements that you've presented to them. You have now baselined the requirements. What does it mean to baseline the requirements in the light of this scenario? Choose the best answer.

  • A. The baseline represents the final collection and approval of all requirements.
  • B. The baseline represents the future set of physical deliverables.
  • C. The baseline represents the approved set of requirements and no additional changes are allowed.
  • D. The baseline represents the approved requirements and any changes must go through a change control system.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
keyss
3 weeks, 2 days ago
Selected Answer: D
The correct answer is D
upvoted 1 times
...
Cheburaators
1 year, 3 months ago
Selected Answer: D
The baseline represents the approved requirements and any changes must go through a change control system.
upvoted 2 times
...
Maddie88
1 year, 5 months ago
Selected Answer: D
The baseline represents the approved requirements and any changes must go through a change control system.
upvoted 1 times
...
Surabhi_26
2 years ago
D is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...