Exam CCBA topic 1 question 32 discussion

Actual exam question from IIBA's CCBA
Question #: 32
Topic #: 1
[All CCBA Questions]

You are the business analyst for your organization. Your stakeholders have recently reviewed and approved the set of requirements that you've presented to them. You have now baselined the requirements. What does it mean to baseline the requirements in the light of this scenario? Choose the best answer.

  • A. The baseline represents the final collection and approval of all requirements.
  • B. The baseline represents the future set of physical deliverables.
  • C. The baseline represents the approved set of requirements and no additional changes are allowed.
  • D. The baseline represents the approved requirements and any changes must go through a change control system.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
teletee
2 weeks, 1 day ago
Selected Answer: D
Baselining requirements means establishing an approved version of the requirements that serves as a reference point for future work. Once baselined, any changes to these requirements must follow a formal change control process to evaluate their impact, gain approval, and maintain traceability. The BABOK Guide (Chapter 5: Requirements Life Cycle Management - Approve Requirements) emphasizes that baselining ensures stability and control over requirements while allowing controlled evolution as needed. This process balances flexibility with governance, ensuring changes are deliberate and aligned with project goals.
upvoted 1 times
...
keyss
5 months ago
Selected Answer: D
The correct answer is D
upvoted 1 times
...
Cheburaators
1 year, 7 months ago
Selected Answer: D
The baseline represents the approved requirements and any changes must go through a change control system.
upvoted 2 times
...
Maddie88
1 year, 9 months ago
Selected Answer: D
The baseline represents the approved requirements and any changes must go through a change control system.
upvoted 1 times
...
Surabhi_26
2 years, 4 months ago
D is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago