Which of the following documents is described in the statement below?
"It is a type of procurement document used to request proposals from prospective sellers of products or services."

  • A. Request for quote
  • B. Request for information
  • C. Request for bid
  • D. Request for proposal
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nobita135
2 weeks, 3 days ago
Selected Answer: D
A Request for Proposal (RFP) is a type of procurement document used by organizations to solicit proposals from potential vendors or service providers. It outlines the project requirements, scope, and evaluation criteria, allowing vendors to submit detailed proposals on how they would meet the organization’s needs, including cost estimates, timelines, and technical solutions.
upvoted 1 times
...
83e7526
3 months ago
Selected Answer: D
I am choosing D, because RFB is not mentioned in BABOK 3, also, when you google the RFB it states that is it RFP.
upvoted 2 times
...
HeenaJain
4 months, 3 weeks ago
request for quote (RFQ): A procurement method of soliciting price and solution options from vendors. - I think answer is A (Request for quote)
upvoted 1 times
...
NorieRose
4 months, 3 weeks ago
Selected Answer: D
Answer: RFP
upvoted 2 times
...
bim_269
1 year, 6 months ago
A request for proposal (RFP), request for quote (RFQ), and request for information (RFI) are three distinct types of documents that businesses and other entities use to reach out to the business community for suppliers or contractors that they may be able to work with. when a company or other organization sends out an RFQ it knows exactly what it needs and is seeking the best supplier or suppliers. An RFP is a more open-ended process. The business or organization is seeking qualified contractors to carry out a new project. The project and its goals are defined in some detail but there is room for creativity in the responses.
upvoted 1 times
...
Mmotun
1 year, 8 months ago
Request for proposal is correct. Bk v3,pg 450
upvoted 1 times
...
NuriaIzard
1 year, 9 months ago
Selected Answer: C
In the next question 204 the procurement document is called "invitation for bid"
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago