Question #: 39
Topic #: 1
[All ECBA Questions]

Which technique is used by business analysts (BAs) to measure the quality of requirements?

  • A. Acceptance and Evaluation Criteria
  • B. Key Performance Indicators
  • C. Risk Analysis and Management
  • D. Entity Relationship Modelling
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
mihaelakasova1
Highly Voted 2 years, 2 months ago
this is a misleading question leading to answer A, not B, since KPIs measure the performance of the requirements.
upvoted 8 times
...
a323bde
Most Recent 3 weeks, 1 day ago
Selected Answer: A
A. Acceptance and Evaluation Criteria
upvoted 1 times
...
alir20
3 months, 1 week ago
Selected Answer: A
verifying the quality of requirements through checking for defined characteristics and relationships
upvoted 1 times
...
herodes
7 months, 1 week ago
Selected Answer: A
A. Acceptance and Evaluation Criteria A. Acceptance and Evaluation Criteria Purpose: To ensure requirements are clear, complete, and testable. They provide a specific benchmark against which the quality of requirements can be measured. Focus: Directly on the quality and completeness of individual requirements. Usage: Used to validate and verify that requirements meet the necessary standards before moving forward in the project lifecycle. B. Key Performance Indicators (KPIs) Purpose: To measure the performance of a project, process, or business activity against defined objectives and goals. Focus: Overall project performance and outcomes rather than the quality of individual requirements. Usage: Typically used to assess the success of a project or business function, including aspects like efficiency, effectiveness, and satisfaction. Supporting Sources:
upvoted 1 times
...
amd112b
9 months, 2 weeks ago
Selected Answer: B
p. 144 Metrics and Key Performance Indicators (KPIs): *used to identify how to evaluate the quality of the requirements*.
upvoted 2 times
...
Freddie_GER
1 year, 3 months ago
Selected Answer: A
Hence, A shoulb be correct IMO
upvoted 1 times
...
Freddie_GER
1 year, 3 months ago
7.3.6 Techniques: "Acceptance and Eval Criteria: used to define the quality metrics that must be met to achieva acceptance by a stakeholder ( p146 )
upvoted 1 times
Freddie_GER
1 year, 3 months ago
A KPI can be a "metric" in the sence of the above
upvoted 1 times
...
...
Adnan8t2
1 year, 7 months ago
Selected Answer: B
144 Metrics and Key Performance Indicators (KPIs): used to identify how to evaluate the quality of the requirements.
upvoted 1 times
...
Hazemnz
1 year, 11 months ago
Selected Answer: B
BABOK page 144
upvoted 2 times
...
missyJ
1 year, 11 months ago
Metrics and Key Performance Indicators (KPIs): used to identify how to evaluate the quality of the requirements. Correct.
upvoted 2 times
...
Lindie_Botha
1 year, 11 months ago
Metrics and Key Performance Indicators (KPIs): used to identify how to evaluate the quality of the requirements BABOK page 154
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago