The answer is correct. The question says 'a document' and not a 'task'. A project charter is a document that houses the project scope statement, but I understand that this is not a BABOK question.
Ans:D The project charter is drafted after the project proposal has been approved and right before the project scope is defined. It follows the natural order of approvals and hierarchy for budget approvals.
not mentioned that's why it is wrong answer. Answer is Scope Statement
upvoted 1 times
...
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Ugo_jay
3 months, 1 week agoSVK2310
9 months, 2 weeks agoNikolaBA
7 months, 2 weeks agoNuriaIzard
1 year, 3 months agoMFZZ
1 year, 10 months agoNikolaBA
7 months, 2 weeks ago