Which of the following is a visual decomposition of the program scope and the resources needed in order to create the things defined within the program scope?
The Work Breakdown Structure (WBS) is a visual decomposition of the project or program scope. It breaks down the work into smaller, manageable components or tasks. The WBS organizes and defines the total scope of the program by dividing it into hierarchical levels, detailing both the work to be done and the resources needed to complete the tasks. It serves as a foundational document for planning, assigning, and tracking the work.
Correct answer is D (WBS).
Justification: A Work Breakdown Structure (WBS) is a visual decomposition of the program scope and the resources needed to create the deliverables defined within that scope. It breaks down the project into smaller, more manageable components, providing a hierarchical representation of the work to be done.
The Resource Breakdown Structure (RBS) is a hierarchical representation of resources organized by resource category or type, such as labor, equipment, materials, or facilities. RBS primarily focuses on resources allocation and categorization rather than decomposing the program scope and deliverables. Further, RBS is not a terminology used in BABOK v3.
Wow - should have looked at the keyword 'resources'
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
EEMartins
1 month agoNobita135
1 month, 3 weeks agoFarooq_95
4 months, 3 weeks agoElyonSenjo
2 years, 2 months agoMFZZ
2 years, 5 months ago