Actual exam question from IIBA's CBAP
Question #: 36
Topic #: 1
[All CBAP Questions]

You are the business analyst for your organization and are working on prioritizing the project requirements. Management has asked you to prioritize the requirements based on the cost-benefit analysis for the requirements' value to the organization.
What basis for prioritization are you using in this instance?

  • A. Business value
  • B. Stakeholder agreement
  • C. Likelihood of success
  • D. Urgency
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MFZZ
Highly Voted 2 years, 11 months ago
Key word is Value
upvoted 5 times
...
AlphaD
Most Recent 2 months, 2 weeks ago
Cost Benefit is Value . A
upvoted 1 times
...
wokeupsalarymen
9 months, 3 weeks ago
Cost-Benefit = Value
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago