Which of the following is a method of displaying the timelines of all the various subtasks that are involved in any project?

  • A. Pie chart
  • B. Scatter chart
  • C. Activity network diagram
  • D. Cost-benefit analysis
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AlphaD
1 month, 1 week ago
Selected Answer: C
Not CBAP v3 Test related. Skip. Thanks Examtopics.
upvoted 1 times
...
Farooq_95
8 months, 3 weeks ago
Selected Answer: C
The correct answer is Activity Network diagram. However, this diagram is not described in BABOK v3. Its definition is "An activity network diagram is a graphical representation of the sequence and dependencies of the project activities. It shows the start and end points of each activity, the duration and resources required, and the logical relationships between them." None of the other diagrams include timelines of various tasks so Activity Network Diagram is the only possible option.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago