Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam CBAP All Questions

View all questions & answers for the CBAP exam

Exam CBAP topic 1 question 106 discussion

Actual exam question from IIBA's CBAP
Question #: 106
Topic #: 1
[All CBAP Questions]

Management would like you to front-load the requirements with the most risk requirements.
Why would management prefer the risky requirements first in the prioritization?

  • A. So if the risk comes true the project will fail will little investment in the work.
  • B. So if the risk comes true then the project manager can mitigate the risk event.
  • C. So if the risk comes true they'll receive the reward as soon as possible.
  • D. So if the risk comes true then there's ample time to correct the problem.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nekdre
Highly Voted 2 years, 9 months ago
The requirement that is most difficult to implement may be prioritized to the top of the list in order to minimize the resources that are spent before learning that a proposed solution can not be delivered
upvoted 5 times
...
CBAPCohort6
Most Recent 1 month, 1 week ago
Selected Answer: D
D. So if the risk comes true then there's ample time to correct the problem. Management prefers to address the requirements with the most risk first because it allows for early identification and mitigation of potential issues. This approach provides sufficient time to implement corrective measures before they can significantly impact the project's success​.
upvoted 1 times
CBAPCohort6
1 month, 1 week ago
If there is a risk that the solution is not technically feasible, the requirement that is most difficult to implement may be prioritized to the top of the list in order to minimize the resources that are spent before learning that a proposed solution cannot be delivered.... I think the answer is A
upvoted 1 times
...
...
SaintTC
9 months, 3 weeks ago
5.3.4 -If there is a risk that the solution is not technically feasible, the requirement that is most difficult to implement may be prioritized to the top of the list in order to minimize the resources that are spent before learning that a proposed solution cannot be delivered.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...