Tracy is a business analyst for her organization and she's gathered and identified the needed requirements for the solution scope. What must Tracy do before she can begin managing the requirements? Choose the best answer.
A.
Tracy must decompose the requirements in WBS.
B.
Tracy must create cost-benefits analysis of each requirement to manage the benefits first.
C.
Tracy must identify roles, responsibilities, and owners of the requirements to fully manage the requirements.
D.
Tracy must communicate the requirements to the stakeholders for their consent and approval.