Exam CBAP topic 1 question 50 discussion

Actual exam question from IIBA's CBAP
Question #: 50
Topic #: 1
[All CBAP Questions]

Henry is the business analyst for his organization. Management has created a pre-determined budget of $450,000 for his solution. Henry has identified the project requirements but now wants to prioritize them based on timeboxing and budgeting. Henry examines the cost of the requirements and begins removing the requirements from the allowed list in order to meet the $450,000 budget.
What timeboxing or budgeting approach is Henry using?

  • A. Parametric
  • B. All in
  • C. Selective
  • D. All out
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Nobita135
1 month ago
Selected Answer: C
Henry is using the Selective approach to timeboxing and budgeting. In this approach, the business analyst prioritizes requirements by evaluating their costs and removing less critical or lower-priority requirements until the project fits within the allocated budget or time constraints. This ensures that the most valuable and essential requirements are included while staying within the budget limit of $450,000.
upvoted 2 times
...
CBAPCohort6
2 months, 4 weeks ago
All in - Option B
upvoted 1 times
...
Typhat
11 months ago
Selected Answer: B
All In – You start by including all the requirements necessary for the solution to be developed and then remove/postpone the requirements whose implementation will cause the project to exceed the deadline.
upvoted 1 times
...
Iron79Man
1 year, 2 months ago
I think that it's Selectable as based on the allocated budgeted , certain requirements have been selected to move one. It wasn't mentioned that the least expensive will be selected , or most expensive ones. Therefore it's selective , not based only on the budget but other parameters' like requirements dependencies
upvoted 1 times
...
rmr29
1 year, 2 months ago
Pg. 312: BA information Time Boxing: based on allocation of a fixed resource (time or money)
upvoted 1 times
...
ElyonSenjo
2 years, 8 months ago
BABOK v2
upvoted 1 times
...
Spartanxxv
2 years, 8 months ago
Selected Answer: B
Parametric is an element under Estimation. This is talking about prioritization where timeboxing is listed in BABOK v3 pg. 313
upvoted 4 times
...
Dillon91
2 years, 8 months ago
A: BABOK v3 pg 272
upvoted 1 times
...
Nattie14
2 years, 11 months ago
Selected Answer: A
The other approaches are not in the BABOK v3
upvoted 2 times
...
zoltrixound
3 years ago
Selected Answer: A
Babok v3 pg 272, Parametric is the only approach defined in the book.
upvoted 3 times
...
zoltrixound
3 years ago
Babok v3 pg 272, Parametric is the only approach defined in the book.
upvoted 1 times
...
Dillon91
3 years ago
Selected Answer: A
Others do not exist in the babok
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago