Henry is the business analyst for his organization. Management has created a pre-determined budget of $450,000 for his solution. Henry has identified the project requirements but now wants to prioritize them based on timeboxing and budgeting. Henry examines the cost of the requirements and begins removing the requirements from the allowed list in order to meet the $450,000 budget.
What timeboxing or budgeting approach is Henry using?
jay_de
1 week, 5 days agosuwaidsy89
1 week, 6 days agoGr3n1
2 months agoPuneet1503
3 months agoNobita135
4 months, 1 week agoCBAPCohort6
6 months, 1 week agoTyphat
1 year, 2 months agoIron79Man
1 year, 5 months agormr29
1 year, 6 months agoElyonSenjo
2 years, 11 months agoSpartanxxv
2 years, 12 months agoDillon91
3 years agoNattie14
3 years, 2 months agozoltrixound
3 years, 4 months agozoltrixound
3 years, 4 months agoDillon91
3 years, 4 months ago