Exam CBAP topic 1 question 319 discussion

Actual exam question from IIBA's CBAP
Question #: 319
Topic #: 1
[All CBAP Questions]

The business sponsor of a project to automate a high risk, high profile process has expressed concerns that some activities people perform will be missed. The business analyst (BA) has already created a process flow with associated user stories.
Which of the following actions will address the sponsor's concerns?

  • A. Record the concerns in the risk register
  • B. Schedule a formal review with the stakeholders
  • C. Demonstrate traceability to the business case
  • D. Review the final approved elicitation results
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
786NB786
Highly Voted 2 years, 6 months ago
Selected Answer: B
SChedule review to confirm the requirements
upvoted 6 times
...
Gabosky
Highly Voted 1 year, 5 months ago
Selected Answer: C
Page 80: Requirements: may be traced to other requirements (including goals, objectives, business requirements, stakeholder requirements, solution requirements, and transition requirements), solution components, visuals, business rules, and other work products.
upvoted 5 times
...
NgocThanh
Most Recent 1 week, 2 days ago
Selected Answer: B
C. Demonstrate traceability to the business case: • Why not: Demonstrating traceability to the business case ensures that the project aligns with the business objectives, but it does not directly address the sponsor’s concern about missing activities. This step is typically done to confirm alignment with the overall goals, not to verify process completeness.
upvoted 1 times
...
SaintTC
4 months, 3 weeks ago
Answer is B- In this scenario, the project sponsor is worried about the possibility of overlooking certain tasks performed by people in the automated process, rather than being concerned about the business case.
upvoted 3 times
...
Gilism
8 months, 3 weeks ago
"C" - Business Cases: used to capture information regarding the business need and opportunity. A business case captures the rationale for undertaking a change. Traceability to Business case will help the sponsor's understanding of the need, opportunity, and rationale behind the action.
upvoted 1 times
...
[Removed]
10 months ago
Selected Answer: C
C: (P79) Traceability enables: reliable assessment of which requirements have been addressed and which have not.
upvoted 1 times
...
SAJEESHKUMAR
1 year, 4 months ago
test CCCCCC
upvoted 2 times
...
Hobic
1 year, 11 months ago
C. Demonstrate traceability to the business case
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.