You have identified a task in your task list that cannot be completed until the inspector for the project signs off on the initial deliverables. The inspector's signoff on the initial deliverables is called what?
Suggested Answer:Answer: A is incorrect. A constraint is anything that limits the current options, such as deadline or predetermined budget.🗳️
The current task is dependent on the preceding task of the inspector signing off on the deliverables. list, but it does not answer this question.
BABOK Section 6.3.2: Define Solution Scope, a dependency refers to a relationship between two activities or tasks where one task cannot begin or continue until another task is completed. In this case, the task in question cannot proceed until the inspector signs off on the initial deliverables. The signoff is therefore a dependency, as it is a prerequisite that must be fulfilled before the subsequent task can proceed.
D. constraint. The signoff is not dependent on the project deliverable, rather the project deliverables are dependent on the signoff, hence the signoff is acting as a constraint to the completion of the project
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
17b7c4c
1 month, 1 week agoMoathov
11 months, 4 weeks agoSty8
2 years, 9 months agoMoathov
11 months, 4 weeks agosaeedddddd
3 years ago