Which of the following is the formal acceptance of the project?

  • A. A project review
  • B. A sign-off
  • C. Risk assessment
  • D. Inspection trend analysis
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
OctavianG
3 months, 1 week ago
Business analysts are responsible for obtaining stakeholder approvals and are required to understand who holds decision-making responsibility and who possesses authority for sign-off across the initiative.
upvoted 2 times
OctavianG
2 months, 1 week ago
Project sign-off is one of the many activities you'll do at the end of a project. This is the phase where you've handed over all deliverables and are about to dismiss the project team. The typical steps in this phase include: Project sign-off and completion of all other legal formalities.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago