What requirements elicitation involves carefully selected stakeholders and subject matter experts for a short, intensive period (usually for one to a few days) to define and document the requirements for a solution?
As per BABOK v3 10.50.2, a workshop is a focused event attended by key stakeholders and subject matter experts (SMEs) for a concentrated period of time.
B - pg 452 - Glossary - Requirements workshop: A structured meeting in which a carefully selected group of stakeholders collaborate to define and/or refine requirements under the
guidance of a skilled neutral facilitator.
Focus groups has participants willing to offer both insights and perspectives on specific topics and listen to other participant opinion typically last for 1 to 2 hours with 6-12 attendees while workshop is for carefully selected key stakeholders and SMEs for a short intensive period (typically 1 or a few days)
answer is B- short ,intensive period from 1 to 4 days are they key phrase here
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Farooq_95
2 months, 3 weeks agoRabbitsfoot
4 months agob9adaf1
5 months agobim_269
1 year, 6 months agobim_269
1 year, 6 months agobinu801
2 years, 11 months ago