You are the business analyst for your organization and preparing to complete the requirements elicitation activities. Your manager wants to know when the requirements elicitation process will be completed.
Which of the following responses best describes the nature of the requirements elicitation process?

  • A. The schedule of the project determines the duration of the requirements elicitation process .
  • B. The duration of the requirements elicitation activities is determined by the willingness of the project stakeholders to contribute to the requirements information.
  • C. The size of the project determines the duration of the requirements elicitation process.
  • D. Eliciting requirements is not a compartmentalized activity.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Farooq_95
3 months ago
Correct answer is D. As per BABOK v3 pg 53, Elicitation and collaboration work is never a 'phase' in business analysis; rather, it is ongoing as long as business analysis work is occurring. Elicitation and collaboration can be planned, unplanned, or both.
upvoted 1 times
...
Typhat
5 months, 1 week ago
Selected Answer: D
Elicitation activity is not phased. Rather it can occur at any point during the project
upvoted 1 times
...
nitin_rico
1 year, 8 months ago
IF THERE IS NO LIMIT THEN HOW pm WILL KNOW WHEN A REQUIRMENT ELICITATION WILL BE OVER ? HERE i AM ASSUMING REQ. ELICITATION WORK FOR SPECIFIC CONTEXT? OTHER WISE IT WILL KEEP GOING
upvoted 1 times
...
Fedara
2 years, 1 month ago
Selected Answer: D
Elicitation and collaboration work is never a 'phase' in business analysis; rather, it is ongoing as long as business analysis work is occurring. BABOK v3, pg 53
upvoted 2 times
...
Fedara
2 years, 1 month ago
Selected Answer: D
There is no start and stop date
upvoted 2 times
...
CBAP_Exam
2 years, 6 months ago
No option B cannot be the right one. As keeping stakeholders interest at business analysis activities is one of the primary roles of a Business Analyst. For me option D is correct.
upvoted 1 times
...
NickMane
2 years, 9 months ago
B is also good answer
upvoted 2 times
...
cc2104
2 years, 11 months ago
4.0 Elicitation and collaboration work is never a 'phase' in business analysis; rather, it is ongoing as long as business analysis work is occurring. Eliciting business analysis information is not an isolated activity.
upvoted 3 times
...
timojeaga
2 years, 12 months ago
The answer looks more like C. The side of the project, determines the duration of the requirement elicitation since the PM wants to know how long it will take for the process to be completed
upvoted 1 times
...
binu801
3 years ago
Can anyone explain why D is the answer. For me the answer should be B
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago