The question pertains to PMBOK. Its V7 defines Responsibility Assignment Matrix (RAM) as a grid that shows the project resources assigned to each work package.
In the context of BABOK v3, RACI chart is correct answer because it involves assigning the RACI designation in order to specify the level of responsibility expected from each stakeholder and/or group. BABOK v3 does not define RAM.
RACI and RAM charts are technically the same. But for the sake of BABOK, it should be RACI because the Responsibility Assignment Matrix is under PMBOK.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
AlphaD
2 weeks, 5 days agoFarooq_95
7 months agoDoktorKross
1 year, 7 months agoDillon91
1 year, 9 months agoHong_i
2 years, 2 months agoNickMane
3 years, 2 months agoEky
3 years, 4 months agoNickMane
3 years, 4 months ago