A business analyst (BA) is in the process of allocating requirements to various releases of a solution. On what should the BA base requirements to maximize the value of the solution?
A.
Priority set by stakeholders
B.
Available resources
C.
Timing of the release and its impact on business
Ans is C. Pg 155.
The value of a solution might vary depending on how
requirements are implemented and when the solution becomes available to
stakeholders. The objective of allocation is to maximize that value.
Timing of the release and its impact on business is correct. As per BABOK v3 7.5.4.3, the value of a solution might vary depending on how requirements are implemented and when the solution becomes available to stakeholders. The objective of allocation is to maximize that value.
The "when solution becomes available" represents the timing of release and "how requirements are implemented" represents the impact on business value.
changed my mind - correct answer is C. There is no specific reference to whether the scope has been defined or not... therefore the most suitable answer is C. The BA can maximize the overall value of the solution by aligning requirements with the bss goals and objectives for each release.
If there's no predefined scope for each release, then considering the components in scope for that release (Option D) becomes a more significant factor in the requirements allocation process. In such a scenario, the BA would need to assess which requirements and components can feasibly be included in each release based on factors like available resources, technical dependencies, and project timelines. By focusing on the components in scope for each release, the BA ensures that the allocated requirements align with the immediate goals and objectives of that particular release.
Therefore, in the absence of a predefined scope for each release, Option D becomes a more appropriate consideration for maximizing the value of the solution through effective requirements allocation.
changed my mind - correct answer is C. There is no specific reference to whether the scope has been defined or not... therefore the most suitable answer is C. The BA can maximize the overall value of the solution by aligning requirements with the bss goals and objectives for each release.
should be C. if you read the question carefully 'BA is in the process of allocating requirements to various releases of a solution' - this means no scope for each release yet.
Should be D
Requirements allocation is the process of assigning requirements to solution components and releases to best achieve the objectives.
Then, components should be in release to be allocated
I change my mind.
BABOK 7.5.4.3. Requirement may be allocated between organizational unit, job function, solution components, or releases of a solution.
Confuse on the question, what's asking for?
From 7.5.3
Requirements allocation is the process of assigning requirements to solution components and releases to best achieve the objectives. Allocation is supported
Define Design Options
by assessing the trade-offs between alternatives in order to maximize benefits and minimize costs. The value of a solution might vary depending on how requirements are implemented and when the solution becomes available to stakeholders. The objective of allocation is to maximize that value.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
[Removed]
Highly Voted 3 years, 1 month agokevinhahaha
Highly Voted 3 years, 4 months agoFarooq_95
Most Recent 2 months, 3 weeks agoRabbitsfoot
3 months, 1 week agoRabbitsfoot
4 months agoRabbitsfoot
3 months, 1 week agoWlkkkk
1 year, 7 months agoOlivierPaudex
2 years, 3 months agoOlivierPaudex
1 year, 8 months agosaeedddddd
2 years, 7 months agorupakarthik
3 years, 2 months agoHobic
1 year, 11 months agokevinhahaha
3 years, 4 months ago