As part of defining the business analysis approach for a project, the business analyst (BA) identifies the key stakeholders responsible for upcoming activities for the initial phase. The BA emails each of these stakeholders and asks when they can be finished. One stakeholder does not reply, one angrily comments that it is not their job and is too busy, and two respond saying that they do not understand what is being asked of them.
What competencies can the BA draw on that would best assist with getting agreement from all these stakeholders?

  • A. Personal accountability, time management, demonstrated trustworthiness
  • B. Negotiation, conflict resolution, effective communication
  • C. Industry knowledge, solution knowledge, organization knowledge
  • D. Learning, creative thinking, problem solving
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
HappyA
Highly Voted 2 years, 5 months ago
Pg no 73 Option B is correct
upvoted 7 times
...
786NB786
Highly Voted 1 year, 7 months ago
Selected Answer: B
B=Negotiation, conflict resolution, effective communication
upvoted 6 times
...
Nonny1
Most Recent 6 months ago
BABOK 4.5.4.1 Pg 73. Answer is B
upvoted 5 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago