exam questions

Exam CBAP All Questions

View all questions & answers for the CBAP exam

Exam CBAP topic 1 question 87 discussion

Actual exam question from IIBA's CBAP
Question #: 87
Topic #: 1
[All CBAP Questions]

Which of the following is an estimate based on past projects to predict the current cost and/or duration of the current project?

  • A. Current estimate
  • B. Past project cost
  • C. Past estimate
  • D. Top-down estimate
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
KEN_ELELEGWU
1 month, 3 weeks ago
Selected Answer: D
The correct answer is D. Top-down estimate. A top-down estimate is an estimate based on past projects or experiences, where the estimator uses historical data to predict the cost and/or duration of the current project. This approach involves using high-level, overall project metrics from previous projects to estimate the current project's costs and duration. Top-down estimates are often used when there is limited information available about the current project, or when the project is similar to previous projects. The other options are not correct because: - A. Current estimate: This is an estimate based on the current project's specific details and requirements. - B. Past project cost: This refers to the actual cost of a previous project, rather than an estimate. - C. Past estimate: This refers to an estimate made in the past, rather than an estimate based on past projects.
upvoted 1 times
...
CBAPCohort6
4 months, 4 weeks ago
Selected Answer: D
D. Top-down estimate A top-down estimate is based on past projects to predict the current cost and/or duration of the current project. It uses high-level information from similar previous projects to estimate the overall cost and schedule​
upvoted 1 times
...
Rfcuenca
1 year, 1 month ago
Babok v2 Pages 170, 171 Top-down estimate is equal Analogous Estimate. Past Estimate Doesn't exists
upvoted 1 times
Rfcuenca
1 year, 1 month ago
Option D
upvoted 1 times
...
...
subyottun
1 year, 2 months ago
I think D was selected as the answer in the context of estimating the current cost based on estimation performed early in the project life cycle when detailed information is limited and relies on high-level assumptions, analogous estimation, or historical data from similar projects.
upvoted 1 times
...
NuriaIzard
2 years, 5 months ago
They probably really meant B as it says that the estimation should be based on previous project costs and experience
upvoted 1 times
...
Shreejith
2 years, 8 months ago
Top Down: examining the components at a high level in a hierarchical Breakdown. None of the options are correct. Delphi estimation technique uses a combination of expert judgment and history.
upvoted 2 times
...
Nwazuluaru
2 years, 9 months ago
Top down estimating approach deals with how long the project will take to completion then breaking them into various tasks. Bottom up deals with estimating how long it take each sub task to complete
upvoted 1 times
...
ElyonSenjo
2 years, 10 months ago
Only top-down among the list is an estimation technique
upvoted 1 times
...
subha_CBAP
4 years, 1 month ago
Top-down: examining the components at a high level in a hierarchical breakdown.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago