A large insurance company wants to buy a new claims processing system or upgrade one of its two existing systems. Each year the claims department is given a
$3,5 million budget to spend. Time is of the essence since there are some regulatory changes that will be coming the following year that will require several features that currently neither one of the two claims systems currently support.
There are eight stakeholders involved in this initiative. There are local to where the claim systems are managed, while five are located across the country. The business analyst (BA) struggled to get all stakeholders to agree on the desired features but ultimately got agreement on ten identified key features for the new claims systems. The BA was able to build a current state and future state process model which included all ten key features.
System A processes 75% of the company's claims. It is 5 years old and the claim processors love it because it is easy to use. However it must go offline for two hours each day. The code is very modular so it does have flexibility to be modified. To upgrade system A to have all ten features it would cost %5 million. System
A would be at capacity if it were to process all of the company's claims.
System B processes 25% of the company's claims. It is an older mainframe system, but rarely goes offline. It could easily handle double the number of claims that system A processes. However, it has a lot of legacy code and would cost $6 million to upgrade.
Both systems have some of the ten desired key features. But neither system has all ten. The cost to buy a new system would be $7 million.
Below is the estimated cost for each feature in priority order.

If the budget for the initiative was firm, what is a feasible solution to make sure the project stays within budget?

  • A. Upgrade system B with the first 8 features
  • B. Buy the new system with only the first 5 features
  • C. Upgrade system A with the first 8 features
  • D. Buy the new system with only the first 7 features
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
siliconvalleykam
Highly Voted 3 years ago
B is the answer. Option A - 5465K Option B 3460K Option C 4155k Option D 5400k So only Option B is coming under the Budget 3.5 million
upvoted 15 times
hhh000
5 months, 3 weeks ago
I agree answer is B. But each option Option A - 4065K Option B 3460K Option C 4155k Option D 4605k
upvoted 1 times
...
...
Puneet1503
Most Recent 1 month, 1 week ago
Selected Answer: B
Option A - 5465K Option B 3460K Option C 4155k Option D 5400k
upvoted 1 times
...
Jules_Cmrfrd
2 months, 4 weeks ago
Selected Answer: B
the minimal cost is option B 3460K
upvoted 2 times
...
786NB786
2 years, 2 months ago
A system B Add up all the cost of each of the option features (i.e. add up all feature cots for Option A, B and New). Total for System B for 8 features comes to $3.15 million which is within the budget stated of $3.5 million.
upvoted 1 times
786NB786
2 years, 2 months ago
Disregard the above - the correct is B - buy the system with first 5 features which totals to $3,460K
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago