A national branch of a global company is struggling to improve business processes of its Public and Government Affairs (PGA) department. To work with external stakeholders effectively, PGA employees need to collect, manage, and exchange a vast amount of information. Complex cases involve collaboration of many employees from different departments. The ability to share information and to coordinate corresponding activities is crucial for the company's growth plans. Their current tools and practices do not serve the purpose well. The existing system, which was deployed a couple of years ago, has only a few active users. The majority of PGA employees avoid using it because the system is hard to use and lacks needed functionality. Consequently, available information is mostly unstructured and stored either locally or on a shared network drive. Some of the information exists only in a paper form.
The branch's PGA head, who sponsors the project, wants to implement a configurable solution that two other branches successfully deployed several months ago.
Both deployments were done by three solution consultants, who will be available to assist in the project. They will be responsible for tailoring the solution to PGA needs, as well as for training the PGA staff. With their help, the sponsor plans to complete the project in approximately three months.
The solution consultants reside in another country 7 hours ahead of the rest of the project team. They will be available part-time, but are planning two one-week long trips to the PGA central office to conduct initial training and to participate in the final deployment of the system into production. The consultants, in turn, expect a business analyst (BA) to assist in collecting necessary data and defining customization requirements.
What should define the timing of business analysis work in this project?

  • A. Buy-in of the proposed solution
  • B. Approach used by the previous deployments
  • C. Availability of solution consultants
  • D. Overall project schedule
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
siliconvalleykam
Highly Voted 3 years, 5 months ago
C. Availability of solution consultants
upvoted 6 times
...
NgocThanh
Most Recent 6 days, 9 hours ago
Selected Answer: D
The overall schedule matters
upvoted 1 times
...
Rabbitsfoot
3 months ago
Selected Answer: D
Look at the Behavioral Characteristics core competencies outlined in BABOK v3. These competencies include Ethics, Personal Accountability, Trustworthiness, Organization and Time Management, and Adaptability, etc. Given this context, the timing of business analysis work in the project should be defined based on the overall project schedule (Option D). Each of the mentioned behavioral characteristics plays a crucial role in guiding business analysts' activities throughout the project lifecycle. The effectiveness measures associated with these competencies also provide valuable metrics for evaluating the performance of business analysts in their roles. Therefore, understanding and applying these behavioral characteristics, along with considering the overall project schedule, are essential for successful business analysis efforts.
upvoted 2 times
...
TheBusBus
1 year, 3 months ago
Selected Answer: C
C. Availability of Solution Consultants. BABOK V3 3.1.7 "• Domain Subject Matter Expert: can be a source of risk when their involvement is required and availability is lacking. The approach taken may depend on availability and level of their involvement with the initiative."
upvoted 2 times
...
Nandu2023
1 year, 4 months ago
C.Availability of solution consultants Timing of Business Analysis Work Business analysts determine when the business analysis tasks need to be performed and if the level of business analysis effort will need to vary over time. This type of planning includes determining whether the business analysis tasks performed within the other knowledge areas will be performed primarily in specific phases or iteratively over the course of the initiative. The timing of business analysis activities can also be affected by: • the availability of resources, • priority and/or urgency of the initiative, • other concurrent initiatives, or • constraints such as contract terms or regulatory deadlines.
upvoted 2 times
...
mdadewale
2 years, 3 months ago
Selected Answer: C
The availability of resources.
upvoted 1 times
...
rhsdeal
3 years, 2 months ago
I feel the answer should be D based on 9.2.4.3 pg.197 Babok v3 : 3.1.4.4 - Timing of Business Analysis Work Business analysts determine when the business analysis tasks need to be performed and if the level of business analysis effort will need to vary over time. This type of planning includes determining whether the business analysis tasks performed within the other knowledge areas will be performed primarily in specific phases or iteratively over the course of the initiative. The timing of business analysis activities can also be affected by: • the availability of resources, BABOK V-3: 9.2.4.3 Organization and Time Management: Effectiveness Measures - Measures of effective organization and time management include: schedule of work effort and deadlines is managed and communicated to stakeholders, • adherence to the project schedule and the meeting of deadlines…
upvoted 3 times
BirdCatcher
3 years ago
@rhsdeal: "The timing of business analysis activities can also be affected by the availability of resources", so then C "availability of solution consultants" should be the correct answer, right?
upvoted 2 times
...
...
Saira
3 years, 4 months ago
Babok v3 : 3.1.4.4 - Option C is correc
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago