Exam CBAP topic 1 question 394 discussion

Actual exam question from IIBA's CBAP
Question #: 394
Topic #: 1
[All CBAP Questions]

A major manufacturer of popular beverages has appointed a local distributor to serve a specific territory. The demand for the beverages has a pronounced seasonal pattern. The distributor performs well overall, but is repeatedly unable to keep up with fulfilling many customer orders during peak demand periods. The distributor's current delivery capability is stretched to deliver 60 tons of merchandise per day whereas the season's peak demand periods need a daily delivery capability of up to 100 tons.
The distributor is under pressure to fully meet the year-round market demand in order to stay in business. The distributor's management wants to identify and consider more cost-effective options as resorting to adding more trucks and drivers would not be economically feasible.
A business analyst (BA) has spent several days observing and measuring the warehouse activities to understand the situation and to gain insights into possible solutions. The delivery workflow is a four-step process: (1) picking the orders and assembling them on trays, (2) bringing the trays to the loading bay, (3) loading the orders into trucks, and (4) delivering the orders to customers. As the following table illustrates, overall performance depends is dependent on five major resources: (1) the workers who pick the orders and load them into trucks, (2) the tallyers who check the orders, (3) the drivers, (4) the trucks, and (5) eight loading bays (LBs).

If the driver's average throughput is 0.6 tons/hour, how many hours per day would 15 drivers have to work to deliver 100 tons of merchandise?

  • A. 12
  • B. 9
  • C. 10
  • D. 11
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
siliconvalleykam
Highly Voted 3 years, 10 months ago
And D 11, Calc 100/.6 = 166.67 166.67/15 = 11
upvoted 9 times
NickMane
3 years, 2 months ago
11h * 15 drivers = 165hours.. 0,6 tons gets loaded every hour, so 165 * 0,6 = 99tons.. you haven't fulfilled requirement Also 6 upvots hurt a but
upvoted 4 times
...
...
cc2104
Highly Voted 3 years, 3 months ago
Ans A 0.6 x 15 = 9 100/9 = 11,11 hours and the number of hours should be extend to 12 I think that drivers should work 12 hours. Otherwise they wouldn't be able to transfer 100 tons of merchandise
upvoted 8 times
...
75c1943
Most Recent 1 month ago
Ans is D: since its 11.11 it will be rounded off to the lowest no
upvoted 1 times
...
maestro169
1 year, 6 months ago
Selected Answer: A
Ans = A 0.6 x 15 = 9 100/9 = 11.11 hours and the number of hours should be rounded to 12 to accomplish the task of delivery 100tons
upvoted 3 times
...
Yoli22_
1 year, 7 months ago
Selected Answer: D
Ideally the anwser should be 12. But I think per math calculations its 11hr and 11 mins rounded to 11 is 99tons per day. The key information is that the distributor needs to get capacity of up to 100 ton per day. 99 tons per day is sufficient based on this. Hence 11hrs is sufficient. 12 would be over by 8 and that can lead to waste. So 11 is the best answer.
upvoted 4 times
...
Sha7rour
2 years, 2 months ago
Selected Answer: A
Answer is A, they will deliver more than 100 Tons 0.6 * 15 = 9 Tons/H 9*12h + 108 all other answers will not deliver 100 tons.
upvoted 4 times
...
OlivierPaudex
2 years, 8 months ago
The exact answer is 15 drivers * 0,6 tons/hour = 9 tons/hour To deliver 100 tons : 100/9 = 11,11 Answer should be A : 12 hours Again, why is 11 hours the right answer ? Why does Examtopics not correct it, or at least give some explanation
upvoted 3 times
OlivierPaudex
2 years, 2 months ago
Looking to find an answer to this tricky question is this rule : When you approximatively round a number, you always take it without the decimal, so following this rule : 11,11 will be 11. If this is the rule followed by IIBA, then the answer would be 11h.
upvoted 2 times
...
...
Qualms
3 years, 8 months ago
Option D. 11 Throughput (0.6) for one driver = tons per hour (T/H), for 15 drivers and 100 tons = 0.6 x 15 = 100/T, hence, T = 100/9 = 11.11, approx. 11 hrs
upvoted 4 times
NickMane
3 years, 2 months ago
>10 and <11 = ~11, hence >11 is approx 12, you need more then eleven full hours.. 12 is correct
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.