An insurance company wants to implement a business intelligence solution to consolidate data from various different internal systems to provide a better understanding of their customer base.
A business analyst (BA) is engaged to put together a tender (bid) to be sent to various business intelligence providers and implementation partners. Among other information, the business analyst requests the following:
✑ Licensing costs for Year 0 based on meeting 1 Central Processing Unit (CPU) license
✑ Licensing costs for specific user types such as Report Creators. Online Analytical Processing (OLAP) users and Power uses Predicted licensing costs for renewing in Years 1 ad 2

Full implementation costs -

After reviewing the received vendor responses the project team shortlists the candidates to 3 and the BA structures the received information as follows:

The BA also conducts a sensitivity analysis to compare the expected costs should the company's needs grow based on the following information:
Scenario 1: Ten extra report creator, 1 extra OLAP user and 1 extra power user licenses and 2 extra CPU licenses
Scenario 2: Twenty five extra report creator, 1 extra OLAP user and 1 extra power user licenses and 3 extra CPU licenses

What is the time difference in days between the shortest and longest implementation?

  • A. 39
  • B. 51
  • C. 60
  • D. 19
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
siliconvalleykam
Highly Voted 3 years, 6 months ago
Longest implementation (30+60+120)= 210 Shortest 150 Difference 60 Ans- 60
upvoted 15 times
...
50ad632
Most Recent 6 months ago
Highest 210 days Lowest 150 days Difference 210 - 150 = 60 How come the correct answer is 51 please?
upvoted 1 times
...
50ad632
6 months ago
Why is the answer 51 please?
upvoted 1 times
...
Jules_Cmrfrd
8 months, 2 weeks ago
Selected Answer: C
obvious and simple maths 210-150=60
upvoted 1 times
...
HSinghM
11 months, 4 weeks ago
Selected Answer: C
Longest implementation (30+60+120)= 210 Shortest 150 , So 210 - 150 = 60
upvoted 1 times
...
dhvani2101
2 years, 1 month ago
Selected Answer: C
Longest implementation (30+60+120)= 210 Shortest 150 Difference 60 Ans- 60
upvoted 2 times
...
cc2104
2 years, 11 months ago
ans C 30+60+120 - 150 = 60
upvoted 2 times
...
Wak020189
3 years, 5 months ago
Shortest is 159, so B = 51
upvoted 2 times
Wak020189
3 years, 5 months ago
Ignre my above, Shortest is 150, so 60
upvoted 5 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago