Which of the following is a graphical representation of roles and responsibilities of different project team members?

  • A. RACI chart
  • B. Pareto chart
  • C. Resource histogram chart
  • D. Organization chart
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rupakarthik
Highly Voted 3 years, 7 months ago
sorry ans- RACI-----its between project team
upvoted 9 times
...
NorieRose
Most Recent 5 months, 2 weeks ago
Selected Answer: A
RACI chart
upvoted 2 times
...
Dillon91
1 year, 5 months ago
D I think..visual
upvoted 1 times
...
rupakarthik
3 years, 7 months ago
ans-D organizational chart
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.