During a requirements elicitation workshop, a stakeholder raises an issue that is outside of the project's scope. The business analyst (BA) facilitating the workshop should:
A.
note the issue in the Issue Register to be considered by the Project Manager.
B.
ignore the stakeholder's comment and proceed with the agenda.
C.
consider the issue's impact on the project and gain agreement with stakeholders on the next step.
D.
request the stakeholder to explain the issue further so that possible solutions can be discussed.
C. consider the issue's impact on the project and gain agreement with stakeholders on the next step.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
keyss
3 months, 2 weeks ago