The business analyst (BA) has prepared a requirements package and it is now ready to present to the stakeholders. What is the purpose of presenting the package?
A.
To document the project's completion
B.
To define the analysis approach
C.
To verity the project's progress
D.
To ensure a shared understanding of the information
D. To ensure a shared understanding of the information
upvoted 1 times
...