Question #: 151
Topic #: 1
[All CCBA Questions]

You are the business analyst for a new project. Part of this project is for the project team to manually install new workstations through the company's campus.
Based on your research you have determined that the project team can install 25 new workstations per hour. Since there is a fixed amount of time that these workstations need to be installed you are considering adding additional labor for the implementation. You are also considering to adjust the prioritization of the project requirements based on the amount of workstations the project team can install per hour. What does the 25 workstations per hour represent in this scenario?

  • A. Parametric estimate
  • B. Planning
  • C. Report project
  • D. Timeboxing
Show Suggested Answer Hide Answer
Suggested Answer: Answer: B is incorrect. Planning is a generic project management process that plans for the project work. 🗳️
Timeboxing describes the amount of work that the project team is capable of completing in a set period of time.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
keyss
2 weeks, 4 days ago
Selected Answer: A
A. Parametric estimate
upvoted 1 times
...
17b7c4c
1 month, 1 week ago
Selected Answer: A
In this scenario, the 25 workstations per hour is a parametric estimate. Parametric estimation is a technique that uses historical data or predefined rates (such as 25 workstations per hour) to estimate the duration, effort, or cost of a project task. According to BABOK Section 10.30: Estimation, parametric estimates are derived from measurable parameters such as the number of units produced in a set amount of time and can be used to calculate project timelines, costs, or resource needs. By knowing how many workstations can be installed per hour, the business analyst can calculate how long it will take to complete the task and adjust resource allocation or requirement prioritization accordingly.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...