A business analyst (BA) has completed documenting requirements and to save time, recommends sharing the requirements document with the development team to fast-track development immediately. What issue may arise by doing so?

  • A. Stakeholders may refuse the solution.
  • B. Requirements metrics may not be measurable.
  • C. The BA may significantly impact other aspects of the project timeline.
  • D. The business need may change.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
17b7c4c
1 month, 1 week ago
Selected Answer: A
Sharing the requirements document with the development team and fast-tracking development without obtaining stakeholder review and approval can lead to issues where stakeholders may refuse the solution. According to BABOK Section 5.4: Approve Requirements, requirements should be reviewed and approved by relevant stakeholders to ensure they are aligned with business needs, expectations, and objectives. If stakeholders do not have the opportunity to review and validate the requirements, there is a risk that the developed solution may not meet their needs or may not be accepted once completed.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...