Exam CCBA topic 1 question 371 discussion

Actual exam question from IIBA's CCBA
Question #: 371
Topic #: 1
[All CCBA Questions]

A business analyst (BA) is working on a project to provide a temporary solution that will last for two months. The BA is feeling overwhelmed with the work needed to create the huge number of links to provide full traceability from solution requirements to design for this solution. How can the BA justify omitting all possible links?

  • A. Such traceability is at a lower level of abstraction for this project
  • B. The value each link is delivering in this situation is not high
  • C. Traceability is a low priority as the BA has other work to complete
  • D. It is impossible for anyone to confirm if such links are correct
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
17b7c4c
1 month, 1 week ago
Selected Answer: B
In cases where a solution is temporary or short-term, such as a project intended to last only two months, the value of full traceability may not justify the effort required to establish all possible links between solution requirements and design. According to BABOK Section 5.1: Manage Requirements Traceability, traceability should be applied based on the value it provides to stakeholders, the project, and the organization.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...