You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?
Suggested Answer:B🗳️
You would not need the stakeholder register to perform qualitative risk analysis. Qualitative Risk Analysis uses the likelihood and impact of the identified risks in a fast and cost-effective manner. Qualitative Risk Analysis establishes a basis for a focused quantitative analysis or Risk Response Plan by evaluating the precedence of risks with a concern to impact on the project's scope, cost, schedule, and quality objectives. The qualitative risk analysis is conducted at any point in a project life cycle. The primary goal of qualitative risk analysis is to determine proportion of effect and theoretical response. The inputs to the Qualitative Risk Analysis process are:
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
17b7c4c
1 month, 1 week ago